The 8th BANGKOK WATER SUPPLY Improvement Project

Client : The Metropolitan Waterworks Authority (MWA) Administered by : TEAM Consulting Engineering and Management Co., Ltd The MWA is undertaking construction of water supply facilities under the scope of the Eighth Bangkok Water Supply Improvement Project. This addresses the production system; the water transmission system; and the water distribution system. After project implementation, the total water production capacity at the four water treatment plants – Bangkhen, Mahasawat, Samsen and Thonburi – will be upgraded to 6.32 million m³ per day. The main objective is to increase water supply production capacity at the Bangkhen Water Treatment Plant to 400,000 m³ per day and to install additional pumps and related facilities at various pump and distribution stations. Thus, the MWA will be able to extend the water supply service area by another 200 km². The additional capacity will contribute to sufficient water supply capacity up to 2017. TEAM Consulting Engineering and Management Co., Ltd. is engaging in construction supervision and bid evaluation by providing overall guidance for project implementation including pre- and post-qualification of contractors, evaluation of bids, recommendation for contract awards etc.
Metropolitan Water Productivity Enhancement

Client : Metropolitan Waterworks Authority (MWA) Services : Construction Supervision To meet the ever-increasing demand for water supply and water services in Bangkok, Nonthaburi and Samut Prakan, the MWA decided to expand its productivity and transmission tunnel network. TEAM GROUP has been involved in the development of Maha Sawat Water Treatment Plant in Nonthaburi since 1995 and was entrusted, in 2009, with the design of phase 4 and its accompanying transmission conduit. A scheme to increase its productivity was divided into eight phases, each of which was planned to increase daily production capacity by 400,000 cu.m. Upon its completion of phase 4, the plant will be able to produce 1.6 million cu.m./day of water for Bangkok’s Thon Buri side and for Nonthaburi. When all eight phases are finished in 2017, the total production capacity will amount to 3.2 million cu.m./day. TEAM GROUP also supervised the installation of 300 cu.m./minute pump engines at the Pumping Station 3, Bang Khen Water Treatment Plant, a large water plant with a water production capacity of 3.6 million cu.m./day supplying most areas of Bangkok. The installation will enhance the MWA’s water productivity and distribution and help it to meet increasing demand. In the eastern area of Bangkok, we designed and supervised the construction of a 3,200 mm-diameter transmission tunnel from the Highway No. 351 Intersection, running beneath Kanchanaphisek (East portion) Road, to merge with the existing tunnel around Thap Chang Intersection. Water will be distributed through this 13-km long tunnel to those communities which currently rely on groundwater, a cause of land subsidence. The tunnel will also increase water supply for the Lat Krabang and Bang Phli pumping stations and so help to accommodate growth in industrial zones in the vicinity of Suvarnabhumi Airport.
Expansion of Provincial Water Supply, Koh Samui Branch, Phase 1, Part 2

Client : Provincial Waterworks Authority (PWA) Service : Construction Supervision To solve the water supply problem in Koh Samui, the Provincial Waterworks Authority (PWA) decided to expand its provincial water supply service for Koh Samui Branch, Phase 1, Part 2 by installing submarine raw water pipe from Ban Din Daeng Samakkhi, Pak Phraek Sub-district, Don Sak District, Surat Thani Province to Ban Phang Ka in Koh Samui. The project included the installation of high-yield strength steel pipe of 700 mm diameter on Surat Thani main land at the length of 34 km; the installation of submarine PN 10 HDPE pipe of 800 mm diameter at the length of 20 km; and the construction of landfalls of HDPE pipe connecting to the high-yield strength steel pipe at the Phang Ka Bay. The project also covered the design for future connecting points with on-shore pipes, and electrical and controlling systems. TEAM GROUP was assigned as the Project’s construction supervision consultant.
Drainage Tunnel from Saen Saep and Lat Phrao Canals to the Chao Phraya River

Client : IN Joint Venture Co., Ltd. Service : Construction Supervision TEAM GROUP provided quality control services for the construction of the drainage tunnel from Saen Saep and Lat Phrao canals to the Chao Phraya River, by means of which the BMA plans to lessen the ongoing problem of annual flooding in the eastern Bangkok area. This drainage tunnel can rapidly discharge a large volume of flood water and so alleviate flood problems in the 150 km² area of Bang Kapi, Wang Thonglang, Huai Khwang, Din Daeng, Phaya Thai, Saphan Sung, Lat Phrao, Bueng Kum, Khan Na Yao, Lat Krabang and Min Buri. With a total length of 5.11 kilometers, this 5-meter diameter drainage tunnel is at present the longest in Thailand. Starting from the Rama IX swamp and running along Saen Saep Canal, Soi Sukhumvit 71, Sukhumvit Road and Phra Khanong Canal, water is rapidly drained into the Chao Phraya River by the 60 cu.m./second pumping facility installed at the end of the tunnel, which, to avoid impacts on an MRT subway tunnel and on the foundations of surrounding buildings, is at a depth of 27 meters.
Nam Ngum 2 Hydroelectric Power Project, Lao PDR

Client : CH. Karnchang Public Company Limited / SouthEast Asia Energy Limited / Nam Ngum 2 Power Company Limited Services : Detailed Design, Environmental Management and Resettlement Nam Ngum 2 Hydroelectric Power Project is located at Baan Huay Bor, Vientiane. The project was constructed, managed, and supported by a group of Thai investors focused on GMS market. The concrete faced rockfill dam of 181 m in height, and 485 m in length will be built in a steep narrow gorge creating a reservoir of 6,774 Mm3 capacities at the full supply level of 375 msl., and a power house installed with a 615 MW capacity. Three generators with an annual capacity of 2,218 GWh of electricity will be installed. The electricity will be exported to Thailand via the Electricity Generating Authority of Thailand, thus boosting the economy of Lao PDR. The consultants were assigned with the tasks of detailed design, construction supervision, implementation of the environmental management and resettlement action plans for the relocation of about 6,100 ethnic minorities from 17 villages, preparing application for license from the Lao Government, resettlement plan and implementation, as well as environmental management, and job training and development for the new communities.
Khun Dan Prakanchon Dam

Client : Royal Irrigation Department Services : Detailed Design, Construction Supervision In a bid to mitigate the chronic flood and drought problems, the acid soil problem, as well as to provide water resource for consumption and agriculture, HM King Bhumibol Adulyadej had requested the Royal Irrigation Department to construct Khun Dan Prakanchon Dam which is under the Upper Nakhon Nayok Basin Development Project. Though receiving wide protest from scholars and protesters, His Majesty finally solved the situation and made the project acceptable to the people. Completed in 2004, the Dam has a storage capacity of 224 MCM and an area of 185,000 rai is irrigated. TEAM GROUP was assigned to undertake the contractors bidding; review, inspect, and approve the construction drawings; supervise the construction; and transfer the technology via on-the-job training.
The Concession Contract for Wastewater Treatment and Water Recycling Project for the Suan Luang- Sam Yan Area with Chulalongkorn University

Client: Chulalongkorn University Wastewater Treatment and Water Recycling Project is part of SMART 4 – CHULA Smart City which is located in Suanluang – Sam Yan area under the Office of Property Management of Chulalongkorn University (PMCU). The project aims to treat and recycle consumption wastewater. TEAM GROUP was entrusted with the system management, and maintenance, and distribution of treated water for the PMCU during 10-year concession period. This is the first PPP Project that TEAM GROUP is participated. Water recycling system with a capacity of 200 m3/day was installed. Discharged wastewater from CU Terrace and CU I-House will be treated and released into the pond of Chulalongkorn University Centenary Park. Water in the pond will be continuously monitored with IoT (Internet of Things) equipment and the real-time result will be submitted through Cloud system for water quality management and control.
Nam E-Moun Hydroelectric Power Project, Lao PDR

Client: Chaleun Sekong Energy Co., Ltd., Lao PDR and Song Da 5 Joint Stock Company, Vietnam Located in Dak Cheung District, Sekong Province, Lao PDR, the plant has a generating capacity of 129 MW. TEAM GROUP was entrusted with detailed design of geotechnical works as well as surface and underground concrete structures.
Dam Instrumentation for Huai Kho Reservoir, Maha Sarakham Province, Ban Phet Reservoir, Chaiyaphum Province, and Huai Tha Reservoir, Sisaket Province

Client: Royal Irrigation Department Service : Dam Instrumentation TEAM GROUP was entrusted with supply and installation of dam instruments for the Huai Kho Reservoir, Maha Sarakham Province, Ban Phet Reservoir, Chaiyaphum Province, and Huai Tha Reservoir, Sisaket Province to closely monitor dam behavior to ensure its safety from any damages caused by earthquakes, sudden changes in water levels due to heavy rainfall or release of water for irrigation. The following automated instruments were installed: • Piezometers• V-Notch Weirs• Observation Wells• Reservoir Water Level• Data Logger with Automatic Data Transmission System• Weather Stations
Dam Instrumentation for Reservoir Project

TEAM GROUP was entrusted with supply and installation of dam instruments at 15 dams in the Chi River Basin and the Mun River Basin, which are the two major river basins of the northeastern region, to closely monitor dam behavior to ensure its safety from any damages caused by earthquakes, sudden changes in water levels due to heavy rainfall or release of water for irrigation. The following automated instruments were installed: Data Logger with Automatic Data Transmission System